Science Operations Planning and Implementation for the OSIRIS-REx Mission, Part 1: Process

Anjani T. Polit, Sara S. Balram-Knutson, Edward Audi, Tammy Becker, William V. Boynton, David Dean, Kristofer Drozd, Heather L. Enos, Michael Fitzgibbon, Ingrid Galinsky, Rose Garcia, Andrew Gardner, Karl Harshman, Carl W. Hergenrother, John N. Kidd, Diane Lambert, Joshua V. Nelson, Sanford Selznick, Mathilde M. Westermann, Zoe ZeszutDante S. Lauretta

Research output: Chapter in Book/Report/Conference proceedingConference contribution

1 Scopus citations

Abstract

The Origins, Spectral Interpretation, Resource Identification, and Security-Regolith Explorer (OSIRIS-REx) spacecraft arrived at the near-Earth asteroid (101955) Bennu in December 2018 and executed a science observation campaign to comprehensively characterize the asteroid. Proximity operations at Bennu included orbital phases and flyby phases with various viewing geometries and altitudes. The complexity of the mission plan, integrated instrument operations, and the challenges of spacecraft navigation in the microgravity environment required an intricate planning and implementation process that included participation and coordination among all mission elements. The Science Planning Team (SPT) and the Implementation Team (IpT) at the University of Arizona planned and implemented all science and most optical navigation observations. Prior to the formal planning process, science requirements were mapped to mission phases and observation geometry constraints. During development of the mission phases, the navigation team produced a spacecraft trajectory, and the SPT developed the pointing and attitude profile to meet the specified constraints. In the strategic planning process, which began three months prior to execution, the SPT conducted sensitivity analysis of the observation designs against a set of perturbed trajectories delivered by the navigation team to ensure that they were robust to navigational uncertainties. Planning of the specific observations to occur within each phase was divided into units of weeks, and the plans for each week were developed and implemented on a rolling eight-week tactical planning and implementation cycle, ending with execution and data downlink. This cycle included a standardized schedule of activities and gateways to ensure that every observation plan underwent a full suite of analysis, verification, and approval in the allocated timeframe. Checklists guided the SPT and IpT through the build and verification process to confirm plan safety and fidelity. The SPT led the first four weeks of the tactical process, with participation from the IpT and other stakeholders. During the first two weeks, the SPT gathered information from stakeholders, conducted preliminary planning to confirm the science observations were feasible and obeyed spacecraft constraints, and determined how to integrate instrument commanding with the spacecraft pointing profile. The SPT started the final observation design and planning six weeks prior to execution. Once complete, plan walkthroughs were conducted with stakeholders, which culminated in a go/no-go decision to proceed with implementation at the four-week point. In the last four weeks of the tactical planning and implementation process, the IpT led the final processing of science plans with participation from stakeholders. The IpT compiled the plans, performed comprehensive safety checks against established spacecraft and instrument flight rules, and generated flight products and artifacts. After IpT delivered the flight products, the spacecraft team integrated them with the spacecraft sequencing, performed ground testing, and produced an integrated report. IpT reviewed the report, verifying instrument health and safety and confirming nominal plan execution in the ground simulation. The final flight products were uplinked to the spacecraft a few days prior to the execution week. During execution, the IpT and other stakeholders monitored instrument performance and viewed science and navigation data. Resulting science data products were used for operational decisions and science investigations.

Original languageEnglish (US)
Title of host publication2022 IEEE Aerospace Conference, AERO 2022
PublisherIEEE Computer Society
ISBN (Electronic)9781665437608
DOIs
StatePublished - 2022
Event2022 IEEE Aerospace Conference, AERO 2022 - Big Sky, United States
Duration: Mar 5 2022Mar 12 2022

Publication series

NameIEEE Aerospace Conference Proceedings
Volume2022-March
ISSN (Print)1095-323X

Conference

Conference2022 IEEE Aerospace Conference, AERO 2022
Country/TerritoryUnited States
CityBig Sky
Period3/5/223/12/22

ASJC Scopus subject areas

  • Aerospace Engineering
  • Space and Planetary Science

Fingerprint

Dive into the research topics of 'Science Operations Planning and Implementation for the OSIRIS-REx Mission, Part 1: Process'. Together they form a unique fingerprint.

Cite this