TY - GEN
T1 - Impact of rom PSD on the crushing and grinding circuit throughput
AU - Fernandez, F.
AU - Rocha, M.
AU - Kemeny, J.
AU - BoBo, T.
AU - Rodriguez, C.
AU - Fuentealba, R.
N1 - Publisher Copyright:
Copyright © 2015 by SME.
PY - 2015
Y1 - 2015
N2 - Mathematical modeling in conjunction with mineral characterization is widely used as a method for design and optimization of comminution circuits, to simulate the processes of crushing, grinding and classification. An important input parameter to the simulation models is the Run-of-Mine Particle Size Distribution (ROM PSD). The run-of-mine size distributions due to blasting have a great influence on the performance of a semi-autogenous grinding (SAG) mill. In this paper, a mine case study was conducted where there are four primary geologic units and the material properties between the four units vary considerably. Also, the mixture of the four unit that will be mined at any given time also vary considerably. This presents a challenge in terms of optimizing the blasting for mill production throughout the mine life. As part of the case study, field rock mass characterization, laboratory rock mechanics tests, and laboratory breakage tests were conducted. The field characterization and rock mechanics tests provide material properties used to simulate the effect of different blast designs on run of mine particle size distributions (ROM PSD). The JKSimBlast software was used for these simulations. The rock breakage tests provide material properties used to simulate crushing and grinding performance. The JKSimMet software was used for these simulations. The goal of the mine is a mill throughput of 95,000 tonnes (104,720 tons) per day (TPD). Based on this goal, run-of-mine fragmentation analysis was conducted for four blasting designs resulting in powder factors of 0.44, 0.54, 0.64, and 0.94 kg/t. The powder factor of 0.44 represents a standard blasting design, while the 0.54 and 0.64 kg/t designs are high-energy blasts specifically to assist with mill production. The 0.94 kg/t design was investigated for the one geologic unit with very high strength. The results of the run-of-mine fragmentation analysis was then input into a crushing and grinding simulation model to predict the mill throughput for the time periods of 1-5 years and 6-10 years. The results indicate that certain blast designs are able to achieve the 95,000 tonnes TPD (104,720 tons TPD) goal, while other blast designs were not. A standard blast design with a 0.44 kg/t powder factor, for example, was not able to achieve the throughput goal, while a design with a 0.64 kg/t powder factor was able to achieve the goal in both the 1-5 and 5-10 year time periods.
AB - Mathematical modeling in conjunction with mineral characterization is widely used as a method for design and optimization of comminution circuits, to simulate the processes of crushing, grinding and classification. An important input parameter to the simulation models is the Run-of-Mine Particle Size Distribution (ROM PSD). The run-of-mine size distributions due to blasting have a great influence on the performance of a semi-autogenous grinding (SAG) mill. In this paper, a mine case study was conducted where there are four primary geologic units and the material properties between the four units vary considerably. Also, the mixture of the four unit that will be mined at any given time also vary considerably. This presents a challenge in terms of optimizing the blasting for mill production throughout the mine life. As part of the case study, field rock mass characterization, laboratory rock mechanics tests, and laboratory breakage tests were conducted. The field characterization and rock mechanics tests provide material properties used to simulate the effect of different blast designs on run of mine particle size distributions (ROM PSD). The JKSimBlast software was used for these simulations. The rock breakage tests provide material properties used to simulate crushing and grinding performance. The JKSimMet software was used for these simulations. The goal of the mine is a mill throughput of 95,000 tonnes (104,720 tons) per day (TPD). Based on this goal, run-of-mine fragmentation analysis was conducted for four blasting designs resulting in powder factors of 0.44, 0.54, 0.64, and 0.94 kg/t. The powder factor of 0.44 represents a standard blasting design, while the 0.54 and 0.64 kg/t designs are high-energy blasts specifically to assist with mill production. The 0.94 kg/t design was investigated for the one geologic unit with very high strength. The results of the run-of-mine fragmentation analysis was then input into a crushing and grinding simulation model to predict the mill throughput for the time periods of 1-5 years and 6-10 years. The results indicate that certain blast designs are able to achieve the 95,000 tonnes TPD (104,720 tons TPD) goal, while other blast designs were not. A standard blast design with a 0.44 kg/t powder factor, for example, was not able to achieve the throughput goal, while a design with a 0.64 kg/t powder factor was able to achieve the goal in both the 1-5 and 5-10 year time periods.
UR - http://www.scopus.com/inward/record.url?scp=84942241942&partnerID=8YFLogxK
UR - http://www.scopus.com/inward/citedby.url?scp=84942241942&partnerID=8YFLogxK
M3 - Conference contribution
AN - SCOPUS:84942241942
T3 - 2015 SME Annual Conference and Expo and CMA 117th National Western Mining Conference - Mining: Navigating the Global Waters
SP - 524
EP - 528
BT - 2015 SME Annual Conference and Expo and CMA 117th National Western Mining Conference - Mining
PB - Society for Mining, Metallurgy and Exploration
T2 - 2015 SME Annual Conference and Expo and CMA 117th National Western Mining Conference - Mining: Navigating the Global Waters
Y2 - 15 February 2015 through 18 February 2015
ER -